LVS: DELAYS AND COST OVERRUNS ON COTAI

08/28/08 02:28PM EDT
Structural issues appear to be impacting LVS on the Cotai Strip. Apparently, one of the near complete hotels on lot 5 or 6 is not settling properly. I think it will cost $50-100 million to fix and likely delay the opening by about 6 months. It is unclear which hotel it is although I’m assuming it’s one of the hotels to be managed by Starwood (St. Regis or Sheraton) or Shangri-La (Shangri-La or Traders). This delay will push the opening into 2010. More to come.

© 2024 Hedgeye Risk Management, LLC. The information contained herein is the property of Hedgeye, which reserves all rights thereto. Redistribution of any part of this information is prohibited without the express written consent of Hedgeye. Hedgeye is not responsible for any errors in or omissions to this information, or for any consequences that may result from the use of this information.